A Guideline of Earned Value Method (EVM) Implementation as Decision Baseline on Acceleration Solutions for Construction Project Scheduling

Show More
  • Abstract
  • Highlights & Summary
  • PDF
  • Literature Map
  • References
  • Similar Papers
Abstract

Implementing an efficient performance monitoring system is necessary to complete a facility building project on time, on budget, and by established standards and specifications. Inappropriate system monitoring process could lead to project failures such as delay which commonly occurs. If the delay happens, it is necessary to accelerate work productivity to overcome it. Earned value method (EVM) is one of the suggested global standards for measuring project performance. It effectively combines scope, cost, and schedule metrics and can provide a clear picture of the state of the project as of the control date. It also predicts the time prolong and completion budget. This paper proposes a guideline to implement EVM as a decision baseline on acceleration solutions for construction project scheduling by conducting an article review, since the EVM can predict the project’s time estimates at completion (TE). According to the guideline, when arranging network planning based on construction actual work performed, it is essential to use TE as the completion time. From the critical activities in network planning, contractors can conduct the acceleration process such as additional work hours (overtime) and additional manpower. This acceleration scenario later could be implemented in the project as the solution to overcome the delay.

Loading PDF

Similar Papers
  • Research Article
  • Citations6

Cost and Time Analysis Using Earned Value Method in The Construction of Sports Facilities in Kecamatan Kedewan Kabupaten Bojonegoro

  • Dec 29, 2023
  • Asian Journal of Engineering, Social and Health
  • Sanda Praja Riduwan +2
  • PDF
  • Research Article

COST AND TIME ANALYSIS USING EARNED VALUE METHOD ON THE CONSTRUCTION OF THE NATIONAL KEDIRI AIRPORT ACCESS ROAD PHASE 1 KEDIRI - NGANJUK

  • Jan 19, 2024
  • International Journal on Advanced Technology, Engineering, and Information System (IJATEIS)
  • Ichsan Yanuansyah Pramadha +2
  • Research Article

Evaluasi Kinerja Waktu dan Biaya Proyek Melalui Pengaplikasian Metode Earned Value Studi Kasus Pada Pembangunan Ruas Jalan Sp. Armed Rumah-Great Kec. Biru-Biru Kab. Deli Serdang

  • Dec 31, 2024
  • Majalah Ilmiah METHODA
  • Sederhana Laia +2
  • Research Article
  • Citations21

Nurse staffing levels in American hospitals: A 2001 report

  • Feb 01, 2002
  • Journal of Emergency Nursing
  • Carol Ann Cavouras
  • PDF
  • Research Article
  • Citations2

Analysis of Control of Costs and Time with Earned Value Method on Road Maintenance Projects in Palmerah District, West Jakarta

  • May 01, 2019
  • Civil Engineering and Architecture
  • Sandy Radhitya Akbar +3
  • Conference Article

Penerapan Metode Earned Value Analisis (EVA) Pada Proyek Reparasi Kapal

  • Jan 28, 2024
  • Silas Tandi +3
  • PDF
  • Research Article

ANALYSIS OF COST AND TIME PERFORMANCE IN THE WADUNGASRI MARKET CHANNEL NORMALIZATION WORK IN SIDOARJO USING THE EARNED VALUE METHOD

  • Jan 20, 2024
  • International Journal on Advanced Technology, Engineering, and Information System (IJATEIS)
  • Wuri Proboretno +2
  • Research Article
  • Citations29

New Estimates of Hours of Work Per Week and Hourly Earnings, 1900-1957

  • Nov 01, 1963
  • The Review of Economics and Statistics
  • Ethel B Jones
  • Research Article
  • Citations4

Take Care of Yourself: We Need You

  • Mar 10, 2014
  • Journal of Clinical Oncology
  • Rebecca S Guest +1
  • Research Article
  • Citations2

Estimates of incubation and completion times in recrystallization

  • Jan 01, 1987
  • Scripta Metallurgica
  • C.W Price
  • Research Article

EVALUASI KINERJA BIAYA DAN WAKTU PELAKSANAAN MENGGUNAKAN METODE EARNED VALUE (EVM) (Studi Kasus: Proyek Pengendalian Banjir Kali Lamong)

  • Dec 01, 2024
  • Wahana Teknik Sipil: Jurnal Pengembangan Teknik Sipil
  • Ferry Muhammad Annas +3
  • Conference Article
  • Citations1

Intelligent Shop Floor Scheduling by an Improved Genetic Algorithm

  • Jan 01, 2021
  • Qi Zhang +2
  • Research Article
  • Citations112

Childcare Subsidies, Wages, and Employment of Single Mothers

  • Jan 01, 2007
  • Journal of Human Resources
  • Erdal Tekin
  • Research Article
  • Citations2

The relationship between person-vocation fit and burnout among resident physicians: A single-center cross-sectional survey

  • Jun 02, 2025
  • PLOS One
  • Yaotian Fan +7
  • Research Article
  • Citations38

Differences in time use and activity patterns when adding a second job: implications for health and safety in the United States.

  • Jun 12, 2014
  • American Journal of Public Health
  • Helen R Marucci-Wellman +4
Cactus Communications logo

Copyright 2026 Cactus Communications. All rights reserved.