Critical path scheduling of task systems with resource and processor constraints (Extended Abstract)

  • Jan 1, 1980
  • Errol L Lloyd
Show More
  • Abstract
  • Literature Map
  • References
  • Citations
  • Similar Papers
Abstract

Minimum execution time scheduling of unit execution time (UET) task systems with resources has been the subject of several papers over the past few years. Because such scheduling problems are, in general, NP-hard, a variety of heuristic methods for producing schedules have been studied, among them, critical path scheduling. The strongest results to date have been for systems where there is no processor constraint. These results may be utilized for systems with a processor constraint by treating the processors as an additional resource. Unfortunately, in those cases where the number of processors is close to the number of resources, this results in an upper bound which is somewhat misleading. In this paper we investigate the performance of critical path scheduling for UET task systems with resources and a fixed number of processors. An upper bound for the worst case performance of critical path scheduling is given. This bound depends both on the number of processors and on the number of different resources. Moreover, we show that this is the best possible (asymptotic) upper bound.

Similar Papers
  • Research Article
  • Citations4

The worst-case analysis of the Garey–Johnson algorithm

  • Feb 10, 2009
  • Journal of Scheduling
  • Claire Hanen +1
  • Research Article
  • Citations1

Analysis Project Management on Cv. Nbw. Id by Cpm Method (Critical Path Method)

  • Mar 21, 2024
  • Jurnal Sinar Manajemen
  • Hikmad Tullah Ahmad +2
  • Research Article
  • Citations6

Bounds and Approximations for Overheads in the Time to Join Parallel Forks

  • May 01, 1995
  • ORSA Journal on Computing
  • Peter J Downey
  • Research Article
  • Citations35

Preemptive scheduling with variable profile, precedence constraints and due dates

  • Apr 01, 1995
  • Discrete Applied Mathematics
  • Zhen Liu +1
  • Research Article
  • Citations52

Scheduling in and out forests in the presence of communication delays

  • Jan 01, 1996
  • IEEE Transactions on Parallel and Distributed Systems
  • T.A Varvarigou +3
  • Research Article
  • Citations19

Scheduling UET task systems with concurrency on two parallel identical processors

  • Dec 31, 2000
  • Mathematical Methods of Operations Research (ZOR)
  • Peter Brucker +3
  • Book Chapter
  • Citations1

Scheduling Unit Execution Time Tasks on Two Parallel Machines with the Criteria of Makespan and Total Completion Time

  • Jan 01, 2005
  • Yakov Zinder +1
  • Conference Article
  • Citations69

Scheduling parallelizable tasks to minimize average response time

  • Jan 01, 1994
  • John Turek +7
  • Conference Article
  • Citations5

Optimal task scheduler for multi-core processor

  • Oct 01, 2010
  • Vinay G Vaidya +2
  • PDF
  • Research Article
  • Citations24

Integration of Building Information Modeling and Critical Path Method Schedules to Simulate the Impact of Temperature and Humidity at the Project Level

  • Jul 01, 2014
  • Buildings
  • Yongwei Shan +1
  • Supplementary Content

Index to volume 19 (1995)

  • Dec 01, 1995
  • Microprocessors and Microsystems
  • Research Article

Analisis Pengendalian Biaya dan Waktu pada Proyek Konstruksi Menggunakan Critical Path Method (CPM) dan Precedence Diagram Method (PDM)

  • Feb 02, 2026
  • Media Ilmiah Teknik Sipil
  • Ayu Lestari +2
  • Research Article
  • Citations1

ANALISIS PELAKSANAAN PENJADWALAN PROYEK PEMBANGUNAN GEDUNG CLUBHOUSE DENGAN PENDEKATAN CPM DAN PERT PADA PT. XY

  • Apr 30, 2018
  • JKIE (Journal Knowledge Industrial Engineering)
  • Kasid Kasid +1
  • Conference Article
  • Citations106

Efficient approximation algorithms for scheduling malleable tasks

  • Jun 01, 1999
  • Gregory Mounie +2
  • PDF
  • Research Article
  • Citations5

PROJECT SCHEDULING ANALYSIS USING THE CRITICAL PATH METHOD – CASE STUDY: SUBSIDIZED HOUSE CONSTRUCTION PROJECT IN HILL MULYA HOUSING, SAMARINDA CITY

  • Dec 19, 2022
  • INTERNATIONAL JOURNAL ON ADVANCED TECHNOLOGY, ENGINEERING, AND INFORMATION SYSTEM (IJATEIS)
  • Gilang Ramadhan Rakasyiwi +2
Cactus Communications logo

Copyright 2026 Cactus Communications. All rights reserved.