Abstract

With the increasingly fierce market competition, optimizing the construction time-cost of deep and large foundation pit construction projects has become one of the key factors for construction enterprises to remain invincible. By dynamically optimizing the time-cost, the optimal time corresponding to the lowest engineering cost can be found. Based on a comprehensive transportation hub project, considering the time value of capital and the reward and punishment of construction time, a time-cost dynamic optimization model is constructed. Relying on BIM technology, the feasibility of construction plan is analyzed from both qualitative and quantitative perspectives, and the project parameters and resource information is obtained accurately and quickly. Using the MATLAB program, time-cost optimization based on genetic algorithm is carried out, and the static and dynamic optimization results are compared. The results show that the dynamic optimization scheme reduces the total cost by 1.68% while reducing the total construction time by 8.47%. The dynamic optimization scheme extends the construction period by 2 days while reducing the total cost by 89,500 yuan compared to static optimization. The peak value of the fund demand curve before and after optimization has decreased from 128,000 yuan to 127,000 yuan. The time-cost dynamic optimization, considering the time value of capital is more in line with engineering reality, and the optimization results are more reliable and accurate. BIM technology can accurately and quickly obtain project parameters and resource information, solving problems such as complex processes in super deep excavation and huge engineering data statistics. The genetic algorithm can efficiently and accurately search for the optimal solution within the global domain. This study combines BIM technology with the genetic algorithm to solve the dynamic optimization problem of construction period cost for deep and large foundation pits. The research results of this study provide a theoretical reference for the optimization of schedule cost for similar projects.

Loading PDF

Similar Papers
  • Research Article
  • Citations1

Design, construction and analysis for super-wide, deep and large foundation pit

  • Jan 25, 2021
  • Transport and Communications Science Journal
  • Shi Shenjie +5
  • PDF
  • Research Article
  • Citations18

Analysis of Lateral Displacement Law of Deep Foundation Pit Support in Soft Soil Based on Improved MSD Method

  • Jan 01, 2021
  • Advances in Civil Engineering
  • Gang Lei +1
  • PDF
  • Research Article
  • Citations10

Deformation Control of Subway Stations under the Influence of the Construction of Deep and Large Foundation Pits with Composite Support Systems

  • Mar 16, 2022
  • Applied Sciences
  • Hua Peng +5
  • Conference Article

Research on Dynamic Reactive Power Optimization of Distribution Network Based on Modern Mathematical Algorithms

  • Jan 01, 2015
  • Lihong Bai
  • Research Article

Influence of the Dynamic Excavation Construction Procession Rail Transit Projects in Deep and Large Foundation Pits

  • Oct 15, 2013
  • Applied Mechanics and Materials
  • Hong Xiao Wu +4
  • Research Article
  • Citations2

Theoretical analysis and engineering application of the new pile-soil-support system

  • Feb 01, 2021
  • IOP Conference Series: Earth and Environmental Science
  • Lei Han +4
  • Research Article
  • Citations3

Construction Technology and Safety Risk Control Measures of Deep Foundation Pit Excavation

  • Apr 25, 2023
  • Journal of World Architecture
  • Mingmin Jiang
  • Conference Article
  • Citations1

Dynamic Active Power Optimization Strategy in Microgrid Based on Virtual Synchronous Generator

  • Sep 12, 2020
  • Zhang Huaqiang +1
  • Research Article
  • Citations21

Multi-objective non-simultaneous dynamic optimal control for an ejector expansion heat pump with thermal storages

  • Dec 24, 2019
  • Applied Thermal Engineering
  • Fang Liu +6
  • Research Article
  • Citations1

Research on BIM Application in Complex Geological Foundation Pit Engineering——Taking Qianhai Trading Plaza Project as an Example

  • Oct 01, 2020
  • Wenjie Zheng
  • Research Article
  • Citations6

A comparative study on the performance of dissortative mating and immigrants-based strategies for evolutionary dynamic optimization

  • Jun 12, 2011
  • Information Sciences
  • C.M Fernandes +2
  • Research Article
  • Citations8

Multi-objective structure dynamic optimization based on equivalent static loads

  • Jun 02, 2017
  • International Journal on Interactive Design and Manufacturing (IJIDeM)
  • Hui Ma +3
  • Book Chapter
  • Citations9

Model-Based Human Motion Capture from Monocular Video Sequences

  • Jan 01, 2003
  • Jihun Park +2
  • PDF
  • Research Article
  • Citations17

Numerical Analysis of the Influence of Deep Foundation Pit Construction on Adjacent Subway Stations in Soft Soil Areas

  • Jan 01, 2022
  • Advances in Civil Engineering
  • Tao Yang +5
  • PDF
  • Research Article
  • Citations28

Deformation Law of the Diaphragm Wall during Deep Foundation Pit Construction on Lake and Sea Soft Soil in the Yangtze River Delta

  • Jan 01, 2021
  • Advances in Civil Engineering
  • Yuan Mei +6
Cactus Communications logo

Copyright 2026 Cactus Communications. All rights reserved.