Evaluation Cost Over-Run in Construction of CFSPP EPC Contract:

Show More
  • Abstract
  • Literature Map
  • References
  • Citations
  • Similar Papers
Abstract

Coal Fired Steam Power Plant (CFSPP) Project is a complex project that requires multidisciplinary knowledge in its implementation. As a result, cost overruns often occur in its implementation. In Indonesia, most power plant projects are using EPC contracts (Engineering, Procurement, and Construction). The contractor is fully responsible for any failures that may occur during the work implementation period. The aim of this study is to compare the realization of completion costs for CFSPP projects with Bill of Quantity (BoQ) and the factors that influence deviations. This research was conducted qualitatively based on the data obtained. Deviations are calculated based on the difference between completion costs and BoQ. Discussions and interviews were conducted with Project Managers and Site Commercial and Risk Managers who were directly involved in construction phase to determine the causes of cost overruns. The result is that the actual cost incurred in the CFSPP project is 3x the cost listed in BoQ. There are cost overruns in each work group including Civil Works, Mechanical Works, Electrical Works and Others Works. Indirect cost realization is 29.84% of total completion cost. The factors that influence cost overruns are: (i) Contractors do not understand the details of the work to be done, (ii) Changes in design and (iii) Realization volume exceeds initial planned volume. The results of this study are expected to be input in preparing owner estimate for CFSPP projects and adding new risk factor lists in CFSPP during construction phase.

Similar Papers
  • Research Article
  • Citations4

Analysis of the Main Causes of Cost Overruns in Construction Industry in Developing Countries and the UK

  • May 31, 2018
  • International Review of Civil Engineering (IRECE)
  • Waleed Jamal Hamid +1
  • Research Article
  • Citations45

A Fuzzy-bayesian Model for Risk Assessment in Power Plant Projects

  • Jan 01, 2016
  • Procedia Computer Science
  • Muhammad Saiful Islam +1
  • Dissertation
  • Citations3

Modelling Cost Overrun Risks in Power Plant Projects

  • Jan 01, 2019
  • Queensland University of Technology
  • Muhammad Islam
  • Research Article
  • Citations6

Factors Causing Project Cost Overrun in the Telecommunications Industry in Oman

  • Jul 01, 2014
  • International Journal of Information Technology Project Management
  • Zahra A Al Zadjali +2
  • PDF
  • Research Article
  • Citations17

A Coupled Genetic Programming Monte Carlo Simulation–Based Model for Cost Overrun Prediction of Thermal Power Plant Projects

  • Aug 01, 2022
  • Journal of Construction Engineering and Management
  • Muhammad Saiful Islam +4
  • Research Article

Implementation of Risk Management for Coal Switching in Coal Fired Steam Power Plant

  • Oct 19, 2021
  • IPTEK Journal of Proceedings Series
  • Luthfi Yulian Fikri +1
  • Research Article

Examining Project Completion Failures in Road Construction: A Case Study of Kafue and Mazabuka Road

  • May 17, 2025
  • International Journal of Advanced Multidisciplinary Research and Studies
  • Mweene Kambombi +1
  • Research Article
  • Citations2

Water footprint comparison of a naphtha-fired combined cycle power plant and a coal-fired steam power plant.

  • May 06, 2022
  • Environmental monitoring and assessment
  • Sankalp Arpit +2
  • Dissertation
  • Citations3

A study of causes of delay and cost overrun in office construction projects in the eThekwini Municipal Area, South Africa

  • Jan 01, 2015
  • Nafkote Tesfahun Adugna
  • PDF
  • Research Article
  • Citations4

Identifying the Factors Affecting the Cost Management of Road Construction Projects in Tanzania: Review Paper

  • Jan 01, 2022
  • Journal of Civil, Construction and Environmental Engineering
  • Salum Khalid Chamuwange +1
  • PDF
  • Research Article
  • Citations25

An investigation into cost overruns for ongoing building projects in Abuja, Nigeria

  • Jun 01, 2017
  • Acta Structilia
  • Ibrahim Saidu +1
  • PDF
  • Research Article
  • Citations6

Investigating the Causal Relationships between Project Complexities and Project Cost: An Empirical Study from New Zealand

  • Jan 01, 2021
  • Advances in Civil Engineering
  • Linlin Zhao +4
  • Book Chapter
  • Citations5

A Risk Management Approach for Prediction of Contingency Sum for Public-Sector Construction Projects

  • May 28, 2016
  • Terence Lam +1
  • Research Article
  • Citations147

Energy and exergy analysis and optimization of Kalina cycle coupled with a coal fired steam power plant

  • Oct 17, 2012
  • Applied Thermal Engineering
  • Omendra Kumar Singh +1
  • Conference Article
  • Citations5

Consumption Prediction on Steam Power Plant Using Data Mining Hybrid Particle Swarm Optimization (PSO) and Auto Regressive Integrated Moving Average (ARIMA)

  • Oct 01, 2019
  • Rinaldi Rusli +2
Cactus Communications logo

Copyright 2026 Cactus Communications. All rights reserved.