Risk Assessment in PPP Projects by Applying Different MCDM Methods and Comparative Results Analysis

Show More
  • Abstract
  • Highlights & Summary
  • PDF
  • Literature Map
  • References
  • Citations
  • Similar Papers
Abstract

Recently, risk assessment has become one of the most challenging issues in the areas of construction and public-private partnerships (PPPs). To address risk assessment issues, various decision-making techniques have been proposed, each with its own specific disadvantages and advantages. This paper investigates step-wise weight assessment ratio analysis (SWARA), complex proportional assessment (COPRAS), fuzzy analytic network process (FANP), fuzzy analytic hierarchy process (FAHP), fuzzy technique for order of preference by similarity to ideal solution (FTOPSIS), simple additive weighting (SAW) and evaluation based on distance from average solution (EDAS) in order to define how various multi-attribute decision-making (MADM) methods compare when used for risk assessment in PPP projects. For this study, 5 risk assessment criteria and 10 types of risk used in Iranian highway PPP projects were selected. Four suitability and applicability tests were used to measure agreement between the rankings derived from the MADM methods. Final results show that all techniques had approximately the same rankings of risk assessment, with the SWARA, COPRAS, and EDAS methods performing slightly better. The findings of this study will help the parties in PPP and construction projects to select the best risk assessment method.

Loading PDF

Similar Papers
  • Research Article
  • Citations2

Prioritization of risk events in PPP wind power projects using integrated FMEA and Monte Carlo simulation

  • Jun 30, 2021
  • Journal of Construction Engineering, Management & Innovation
  • Emre Caner Akcay
  • Research Article
  • Citations92

Evaluation of quality assurance in contractor contracts by multi-attribute decision-making methods

  • Jan 01, 2017
  • Economic Research-Ekonomska Istraživanja
  • Eva Trinkūnienė +5
  • Research Article
  • Citations13

Turnaround project risk assessment using hybrid fuzzy SWARA and EDAS method: case of upstream oil process industries in Iran

  • Dec 28, 2020
  • Journal of Engineering, Design and Technology
  • Mohammad Reza Moniri +3
  • Research Article

The risk assessment of public-private partnership projects using artificial intelligence algorithms

  • Oct 11, 2024
  • MIR (Modernization. Innovation. Research)
  • S G Sternik +2
  • Research Article
  • Citations65

Risk assessment for public–private partnership projects: using a fuzzy analytic hierarchical process method and expert opinion in China

  • Dec 20, 2016
  • Journal of Risk Research
  • Yan Li +1
  • Conference Article
  • Citations1

Investment Risk Assessment Method of PPP Project Based on QPSO-LSSVM

  • Oct 14, 2020
  • Yue Zhai +2
  • Research Article
  • Citations1

Risk Assessment of Public-Private Partnership Projects Using SMART Financing

  • Sep 27, 2020
  • Economics and Management
  • E V Agamagomedova
  • Research Article
  • Citations11

Risk Assessment of Urban Rail Transit Project Using Interpretative Structural Modelling: Evidence from China

  • Feb 23, 2021
  • Mathematical Problems in Engineering
  • Yuan Gao +1
  • PDF
  • Research Article
  • Citations3

The Impact of Participation in PPP Projects on Total Factor Productivity of Listed Companies in China

  • Jul 07, 2021
  • Sustainability
  • Xiangdong Liu +1
  • Research Article
  • Citations2

Factors affecting the calculations of Return on Investment (ROI) in Public-Private Partnerships (PPP) projects In Egypt

  • Jan 01, 2019
  • The Academic Research Community publication
  • Ibrahim Abdel Rashid +2
  • Research Article
  • Citations51

Output‐based specifications for PPP projects: lessons for facilities management from Australia

  • Feb 15, 2013
  • Journal of Facilities Management
  • Arshad Ali Javed +2
  • PDF
  • Research Article
  • Citations141

Hybrid SWARA-COPRAS method for risk assessment in deep foundation excavation project: an iranian case study

  • Apr 21, 2017
  • JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT
  • Alireza Valipour +4
  • Research Article
  • Citations33

Communication performance challenges in PPP projects: cases of Ghana and South Africa

  • Aug 28, 2019
  • Built Environment Project and Asset Management
  • Titus Ebenezer Kwofie +2
  • Research Article
  • Citations20

Risk Assessment of Logistics Enterprises Using FMEA Under Free Double Hierarchy Hesitant Fuzzy Linguistic Environments

  • Apr 05, 2021
  • International Journal of Information Technology & Decision Making
  • Mengjiao Shen +1
  • Conference Article

Fuzzy Analytic Network Process Approach to Risk Assessment of Public-Private Partnership (PPP) Highway Projects in Developing Countries

  • Jan 01, 2012
  • Research, Development and Practice in Structural Engineering and Construction
  • Valipour A R +3
Cactus Communications logo

Copyright 2026 Cactus Communications. All rights reserved.