Setting procurement safety lead-times for assembly systems

Show More
  • Abstract
  • Literature Map
  • References
  • Citations
  • Similar Papers
Abstract

This paper describes a practical method for setting safety lead-times for purchased components in assembly systems with uncertainty in the supply process. The approach is specifically designed to be used in an MRP procurement environment. A two-stage production model in which suppliers were uncapacitated with stochastic lead times was developed. Then, a combinatorial optimization method that took advantage of structural properties was developed to produce an optimal integer solution of safety lead-times. In addition to yielding a practical lead-time setting tool, the model led to some interesting policy insights: (1) the flexibility achieved by bringing parts in early may have value even in situations with ideal suppliers; (2) purchasing components in batches offers some of the same protection as does safety lead time, but is less precise and subsequently more expensive; and (3) ignoring the complicating issues of MRP procurement results in far from optimal results.

Similar Papers
  • Conference Article
  • Citations4

Analyzing a stochastic inventory system for deteriorating items with stochastic lead time using simulation modeling

  • Dec 01, 2011
  • Mohammadmahdi Alizadeh +3
  • Research Article
  • Citations3

JIT delivery with stochastic lead time

  • Jan 01, 2013
  • Journal of the Operational Research Society
  • J C Hayya +4
  • Research Article
  • Citations25

A vendor-buyer inventory model for defective items with errors in inspection, stochastic lead time and freight cost

  • May 03, 2019
  • INFOR: Information Systems and Operational Research
  • Ivan Darma Wangsa +1
  • Research Article
  • Citations2

Inventory Management with Stochastic Lead Times

  • Dec 10, 2013
  • SSRN Electronic Journal
  • Kumar Muthuraman +2
  • Research Article
  • Citations10

Supply management of high-value components with a credit constraint

  • Jun 25, 2011
  • Flexible Services and Manufacturing Journal
  • Lei Zhao +2
  • Research Article
  • Citations21

A vendor–buyer inventory model with lot-size and production rate dependent lead time under time value of money

  • Apr 28, 2020
  • RAIRO - Operations Research
  • Sumon Sarkar +2
  • Research Article
  • Citations15

A new data-driven framework to select the optimal replenishment strategy in complex supply chains

  • Jan 01, 2022
  • IFAC-PapersOnLine
  • Roberto R Corsini +3
  • Research Article
  • Citations13

Coordination of a single-manufacturer multi-retailer supply chain with price and green sensitive demand under stochastic lead time

  • Apr 15, 2023
  • Decision Making: Applications in Management and Engineering
  • Anamika Dash +2
  • Research Article
  • Citations26

Sustainable multi-biofuel production with stochastic lead time and optimum energy utilization under flexible manufacturing

  • May 15, 2024
  • Computers & Industrial Engineering
  • Biswajit Sarkar +3
  • Research Article

Deep Reinforcement Learning for Optimal Replenishment in Stochastic Assembly Systems

  • Jul 09, 2025
  • Mathematics
  • Lativa Sid Ahmed Abdellahi +4
  • Conference Article

Some Results of Weak Anticipative Concept Applied in Simulation Based Decision Support in Enterprise

  • Jan 01, 2010
  • AIP conference proceedings
  • Miroljub Kljajić +4
  • Preprint Article

Orange cold chain with multiple nutritional components

  • May 24, 2021
  • Muhammad Kamran
  • Research Article

Improvement in the Coupling of Procurement Process and Production Planning by Simulation Under Stochastic Demand and Lead Time

  • Aug 31, 2014
  • International Review on Modelling and Simulations (IREMOS)
  • Abdessamad Douraid Douraid +2
  • Research Article
  • Citations106

A 2-Approximation Algorithm for Stochastic Inventory Control Models with Lost Sales

  • May 01, 2008
  • Mathematics of Operations Research
  • Retsef Levi +2
  • Research Article

A production-inventory model with stochastic lead time and JIT set up cost

  • Jan 01, 2018
  • International Journal of Operational Research
  • Kripasindhu Chaudhuri +2
Cactus Communications logo

Copyright 2026 Cactus Communications. All rights reserved.