Why are the Frequently Reported Delay Factors in Construction Projects Recurring?: A Qualitative Study

  • Abstract
  • Literature Map
  • References
  • Citations
  • Similar Papers
Abstract

Since a construction project involves a huge amount of resources, delays in construction have an unfavorable impact on all stakeholders. Due to the large-scale, specialization, and complexity of construction projects, construction delaysare reported globally. Previous quantitative studies mainly through questionnaires have focused on identifying delay factors. However, the identified delay factors show little difference regardless of time and region, thus, a more fundamental study on theroot causes of the delay is needed. Therefore, this study intends to discuss in depth the causes of delay factors identified in previous studies from professionals’ point of view. According to the interview with the experts, schedule delays are caused by factors such as short initial construction periods, errors in design documents, and rework. The effect of construction delays includes not only work quality degradation and increased risk of workplace accidents, but also the professional ethical dilemma ofmanagers. The experts mention that the construction delay can be alleviated with basic measures such as estimating spare construction period, reviewing design documents before work, and thorough quality control. This paper helps in understanding of the identified construction delays and can provide valuable insights in formulating effective strategies to avoid delays in construction projects.

Similar Papers
  • Research Article
  • Citations2

Mitigation Approach for Significant Causes of Contractor’s Delays in Construction Projects in Sri Lanka

  • Sep 29, 2021
  • Proceedings of International Conference on Business Management
  • P Tharsan +2
  • Research Article

Assessment of Delay Factors in Construction Projects: A Chronological Analysis with Insights from Iraq

  • Sep 17, 2024
  • Passer Journal of Basic and Applied Sciences
  • Gaylan Mustafa Mohammed +7
  • Research Article
  • Citations5

Analysing delay factors in construction projects using Z-number approach: insights from Pakistan

  • Aug 03, 2023
  • Canadian Journal of Civil Engineering
  • Muhammad Nadeem +5
  • PDF
  • Research Article
  • Citations2

Stakeholders’ Insight on the Delay of Constructions Projects in the Makkah Region- KSA

  • Dec 20, 2021
  • The Open Construction & Building Technology Journal
  • Kehlan Salman +1
  • Research Article
  • Citations16

Investigating the causes of construction delay on the perspective of organization-sectors involved in the construction industry of Bangladesh

  • Apr 12, 2022
  • International Journal of Building Pathology and Adaptation
  • Mohammad Nafe Assafi +2
  • Research Article
  • Citations48

Risk factors in oil and gas construction projects in developing countries: a case study

  • Mar 13, 2019
  • International Journal of Energy Sector Management
  • Mukhtar A Kassem +2
  • Research Article
  • Citations1

Causes Of Time Delay In Construction Projects In Libya

  • Dec 01, 2024
  • IOSR Journal of Mechanical and Civil Engineering
  • Mahmoud Mukhtar Ahmad Mukhtar +1
  • Research Article
  • Citations2

Critical Delay Factors in Construction Projects and Their Proposed Solutions from the Perspective of Total Quality Management

  • Feb 03, 2024
  • International Journal of Engineering Trends and Technology
  • Sherif Awad Mohamed Elsherbiny +2
  • Research Article
  • Citations33

Influencing factors indicating time delay in construction projects: impact of firm size and experience

  • May 09, 2019
  • International Journal of Construction Management
  • Ahsen Maqsoom +3
  • PDF
  • Research Article
  • Citations5

Delays of construction projects in Makkah from the point of view of the consultant

  • Apr 11, 2023
  • Journal of Umm Al-Qura University for Engineering and Architecture
  • Abdulrazak Badawi Abdulghafour +1
  • Research Article
  • Citations37

Development of delay mitigation measures in construction projects: a combined interpretative structural modeling and MICMAC analysis approach

  • Jan 02, 2023
  • Production Planning & Control
  • Amílcar Arantes +1
  • Research Article
  • Citations30

Investigating Causes of Construction Delay in Ethiopian Construction Industries

  • Dec 03, 2016
  • Werku Koshe +1
  • PDF
  • Research Article
  • Citations2

Identifying and assessing the impact of 4M1E factors on construction project delays in Afghanistan using structural equation modeling

  • Dec 18, 2024
  • Journal of Umm Al-Qura University for Engineering and Architecture
  • Hijratullah Sharifzada +5
  • Research Article

Identify Causes of Delay and Cost overrun in Residential Construction Projects at Surat Region in India: A Review

  • Mar 26, 2023
  • INTERANTIONAL JOURNAL OF SCIENTIFIC RESEARCH IN ENGINEERING AND MANAGEMENT
  • Kirtankumar R Panchal +3
  • Research Article
  • Citations1

Project Delay Factor Ranking among Contractor, Client and Project Management Consultant in Construction Industry

  • Sep 30, 2021
  • WIDYAKALA JOURNAL OF PEMBANGUNAN JAYA UNIVERSITY
  • Ade Asmi +1
Cactus Communications logo

Copyright 2026 Cactus Communications. All rights reserved.