Automatic Clustering and Multi-Directional Scheduling Scheme for Multi-Mode Scheduling Projects

Show More
  • Abstract
  • Literature Map
  • Similar Papers
Abstract

In this study, a cluster-based heuristic algorithm to solve multi-mode resource constrained project scheduling problem (MMRCPSP) is presented. The MMRCPSPs are usually challenging to schedule because each activity has multiple execution modes with renewable and non-renewable resources that are categorized as an NP-hard problem. In this paper, we propose and apply three ideas to solve an MMRCPSP. Firstly, an MMRCPSP with two objectives namely, makespan and executive cost is converted into a single mode resource-constrained project scheduling problem (RCPSP) with three objectives by relaxing the non-renewable resource constraints and then defining a corresponding penalty value. In the second phase, in the light of precedence and renewable resource constraints, the new RCPSP are scheduled by calling the multi-directional scheduling schemes (multi-dss). In the end, on the basis of three objectives’ value (namely makespan, cost, and penalty value), we defined a density-based fitness function for an evolutionary approach regarding the clustering methods on the new solution space. Our numerical results showed that the multi-dss with higher dimension regarding the automatic cluster-based fitness functions affected the performance of the evolutionary approach. Furthermore, the evolutionary approach based on multi-directional scheduling schemes prevents to trap into the local optimums by increasing the solutions’ diversity.

Similar Papers
  • Research Article
  • Citations182

An efficient hybrid genetic algorithm for scheduling projects with resource constraints and multiple execution modes

  • Nov 20, 2008
  • International Journal of Production Economics
  • Antonio Lova +3
  • Book Chapter
  • Citations7

An Organizational Cooperative Coevolutionary Algorithm for Multimode Resource-Constrained Project Scheduling Problems

  • Jan 01, 2014
  • Lixia Wang +2
  • Conference Article
  • Citations1

Probabilistic Model Enhanced Genetic Algorithm for Multi-Mode Resource Constrained Project Scheduling Problem

  • Jul 11, 2015
  • Mayowa Ayodele +2
  • Research Article

Solving MRCPSP by a Hybrid Genetic Algorithm

  • Sep 01, 2013
  • Applied Mechanics and Materials
  • Yan Li +1
  • Research Article
  • Citations1

A Modified Variable Neighbourhood Search Heuristic for the Multi‐Mode Resource Constrained Project Scheduling Problem with A Case Study

  • Jul 01, 2019
  • INCOSE International Symposium
  • Ripon K Chakrabortt +2
  • Conference Article
  • Citations8

BPGA-EDA for the multi-mode resource constrained project scheduling problem

  • Jul 01, 2016
  • Mayowa Ayodele +2
  • Research Article
  • Citations312

A genetic algorithm for the preemptive and non-preemptive multi-mode resource-constrained project scheduling problem

  • Mar 01, 2010
  • European Journal of Operational Research
  • Vincent Van Peteghem +1
  • Book Chapter
  • Citations3

PLA Based Strategy for Solving MRCPSP by a Team of Agents

  • Jan 01, 2016
  • Piotr Jędrzejowicz +1
  • Research Article
  • Citations38

Multi-objective algorithms to multi-mode resource-constrained projects under mode change disruption

  • Feb 07, 2017
  • Computers & Industrial Engineering
  • Sonda Elloumi +2
  • Research Article
  • Citations7

Multi‐start iterated local search metaheuristic for the multi‐mode resource‐constrained project scheduling problem

  • Sep 27, 2021
  • Expert Systems
  • Alfredo S Ramos +2
  • Book Chapter
  • Citations4

Solving Multimode Resource-Constrained Project Scheduling Problems Using an Organizational Evolutionary Algorithm

  • Jan 01, 2015
  • Lixia Wang +1
  • Research Article
  • Citations66

Multi‐mode resource‐constrained project scheduling using modified variable neighborhood search heuristic

  • Feb 27, 2019
  • International Transactions in Operational Research
  • Ripon K Chakrabortty +2
  • Research Article
  • Citations78

Energy-oriented deconstruction and recovery planning

  • Nov 01, 2007
  • Building Research & Information
  • Frank Schultmann +1
  • Research Article
  • Citations37

Artificial Bee colony for resource constrained project scheduling problem

  • Jan 01, 2011
  • International Journal of Industrial Engineering Computations
  • Reza Akbari +2
  • PDF
  • Research Article
  • Citations8

Review of conventional metaheuristic techniques for resource-constrained project scheduling problem

  • Jan 01, 2022
  • Journal of Project Management
  • Amir Golab +3
Cactus Communications logo

Copyright 2026 Cactus Communications. All rights reserved.