Hazard-Based Analysis of Highway Project Development Times

Show More
  • Abstract
  • Literature Map
  • References
  • Citations
  • Similar Papers
Abstract

Transport agencies around the world recognize the importance of on-time on-budget delivery of highway projects and understand the need for an efficient transport development process. Past studies of highway project duration and cost estimation were focused on construction, and few studies have focused on preconstruction project delivery from an agency’s perspective. This paper proposes the use of hazard-based duration models for investigating the potential risk factors that could affect project development time from planning to letting. A database containing over 35 years of highway project data from the state of Indiana was used to develop appropriate models. Of the three model forms (Weibull, Weibull with gamma heterogeneity, and log-logistic) considered in the paper, it was found that the log-logistic model is the most appropriate for modeling project development time. For each work category (pavement, bridge, and road/interchange projects), risk factors were identified, and their influences on project development time (and consequently, on letting time) were investigated. The developed hazard-based duration models were further applied to demonstrate their ability to predict expected project development time for delivery and the project-related factors that influence this duration, thereby providing the agency with a useful interpretation of associated delivery risks.

Similar Papers
  • Conference Article
  • Citations1

Integrated Earned Value Method for IT Project Cost and Duration Estimation

  • May 20, 2023
  • Der-Jiun Pang
  • Research Article
  • Citations12

A Quantitative Analysis of the Performance of Transportation Projects in Developing Countries

  • May 01, 2010
  • Transport Reviews
  • Eduardo A Gamez +1
  • Research Article
  • Citations452

An exploratory study of the effects of supplier relationships on new product development outcomes

  • Nov 29, 2001
  • Journal of Operations Management
  • Marcos A.M Primo +1
  • Research Article
  • Citations51

Practices, barriers and benefits of risk management process in building services cost estimation

  • Mar 01, 1997
  • Construction Management and Economics
  • C K Mok +2
  • Book Chapter
  • Citations2

Structuring a Foundation Basis for Semantic Interoperability in Product Development Process

  • Jan 01, 2016
  • Szejka Anderson Luis +3
  • Conference Article

Reliability testing of structures with road loadings

  • Jun 01, 2012
  • Julio Pulido
  • Conference Article
  • Citations1

The cost estimation of power grid technological transformation project based on Shapley value

  • Mar 04, 2022
  • Yue Lv +3
  • Conference Article
  • Citations3

Using Enhancement Method to Improve Earned Value Index to Achieve an Accurate Project Time and Cost Estimation

  • Apr 01, 2009
  • Iman Attarzadeh +1
  • Single Book

Construction Site Management

  • Aug 12, 2024
  • Dr Ashwini Balakumar +3
  • Research Article
  • Citations14

Impact of project briefing clarity on construction project performance

  • Aug 06, 2020
  • International Journal of Construction Management
  • Ali Vahabi +2
  • Research Article
  • Citations4

Artificial Neural Network Analysis for Cost Estimation of Building Projects in India

  • Jan 01, 2022
  • Proceedings of the International Conference of Contemporary Affairs in Architecture and Urbanism-ICCAUA
  • Ankita Gupta +1
  • Book Chapter
  • Citations1

Estimating the Cost of Industrial Painting Projects

  • Sep 30, 2015
  • Michael P Reina
  • Research Article
  • Citations1

A Review of the Application of Decision Tree Analysis and Artificial Neural Networks in Project Management

  • Apr 22, 2025
  • Jurnal Teknik Industri: Jurnal Hasil Penelitian dan Karya Ilmiah dalam Bidang Teknik Industri
  • Olusina Temidayo Akinyokun +2
  • Conference Article
  • Citations7

Integrated Subsea Supplier-Led Solution: A Case Study

  • Apr 30, 2018
  • F Hurault De Ligny +3
  • Research Article
  • Citations16

A Generic Agent Framework to Support the Various Software Project Management Processes

  • Jan 01, 2007
  • Interdisciplinary Journal of Information, Knowledge, and Management
  • Rita C Nienaber +1
Cactus Communications logo

Copyright 2026 Cactus Communications. All rights reserved.