A Quantitative Analysis of the Performance of Transportation Projects in Developing Countries

Show More
  • Abstract
  • Literature Map
  • References
  • Citations
  • Similar Papers
Abstract

This paper presents the results of a detailed quantitative analysis of performance metrics of a sample consisting of 89 transportation projects sponsored by the World Bank. The sample and a subset consisting of 65 projects were evaluated using the performance metrics of project cost, schedule and scope. The effect of project size (dollar value) and project duration on performance metrics was investigated. Also, the achievement of project goals and potential improvement in planning and estimating over time (the learning effect) was studied. It was found that, in general, in transportation projects sponsored by the World Bank, costs are overestimated and schedules are optimistic. The outcome with respect to cost seems counter‐intuitive because previous work by other researchers had shown a systematic underestimation of project costs. There is significant evidence that there are no efficient controls in place to predict or prevent schedule delays. The study also showed that during the past 15 years, no improvement (learning effect) was evident in project cost and duration estimation as the level of accuracy has not changed significantly. Further, it is observed that project duration did not affect the performance with respect to cost and delay.

Similar Papers
  • Conference Article
  • Citations1

Integrated Earned Value Method for IT Project Cost and Duration Estimation

  • May 20, 2023
  • Der-Jiun Pang
  • Research Article
  • Citations9

Time-cost optimization using harmony search algorithm in construction projects

  • Jan 01, 2019
  • Revista de la construcción
  • Mohammad Lemar Zalmai +2
  • Research Article
  • Citations10

Critical Duration Index: Anticipating Project Delays from Deterministic Schedule Information

  • Nov 01, 2022
  • Journal of Construction Engineering and Management
  • Maria-Carmen González-Cruz +3
  • Research Article
  • Citations47

Exploiting organizational knowledge in developing IS project cost and schedule estimates: An empirical study

  • Jul 31, 2007
  • Information & Management
  • Raymond M Henry +3
  • Research Article
  • Citations29

Calculation of safe float use in risk-analysis-oriented network scheduling

  • Jun 01, 1995
  • International Journal of Project Management
  • Daji Gong +1
  • Research Article
  • Citations8

Scheduling new product development projects using simulation-based dependency structure matrix

  • Jan 01, 2014
  • International Journal of Logistics Systems and Management
  • Mohsen Mohammadi +2
  • Research Article
  • Citations75

Project Scheduling using Dependency Structure Matrix

  • Dec 25, 2004
  • International Journal of Project Management
  • J Uma Maheswari +1
  • Research Article
  • Citations44

Investigating the effect of construction management strategies on project greenhouse gas emissions using interactive simulation

  • Apr 11, 2013
  • Journal of Cleaner Production
  • Pei Tang +2
  • Book Chapter

Simulation Model for Project Duration Estimation with Parameters Extraction Method from Accumulated Data

  • Oct 07, 2019
  • Kazuo Hiekata +2
  • Research Article
  • Citations8

Hazard-Based Analysis of Highway Project Development Times

  • Mar 08, 2012
  • Journal of Transportation Engineering
  • G P Ong +3
  • Research Article
  • Citations58

Data-Driven Machine Learning Approach to Integrate Field Submittals in Project Scheduling

  • Nov 09, 2020
  • Journal of Management in Engineering
  • Mohamad Awada +2
  • Research Article
  • Citations22

Examining the Value of Monte Carlo Simulation for Project Time Management

  • Mar 06, 2018
  • Management:Journal of Sustainable Business and Management Solutions in Emerging Economies
  • Goran Avlijas
  • Research Article

Retrospective BIM performance analysis based on construction big data

  • Jun 03, 2025
  • Engineering, Construction and Architectural Management
  • Berkay Batuhan Bostan +3
  • Research Article
  • Citations1

Predicting project duration using a coupled artificial neural network and Taguchi method approach

  • Jul 11, 2024
  • STUDIES IN ENGINEERING AND EXACT SCIENCES
  • Larbi Bendada +3
  • Conference Article
  • Citations5

Stochastic Method for Forecasting Project Time and Cost

  • May 17, 2012
  • Construction Research Congress 2012
  • Adel Alshibani +1
Cactus Communications logo

Copyright 2026 Cactus Communications. All rights reserved.