An Introduction to the Resource Constrained Project Scheduling Problem Solving Techniques

  • Sep 14, 2016
  • Amaia Lusa +1 more
Show More
  • Abstract
  • Literature Map
  • References
  • Citations
  • Similar Papers
Abstract

A project can be defined as a set of activities. Each activity needs a certain amount of time (that can be variable or even stochastic) and requires different type and quantity of resources (tools, personnel, money, etc.). Also, usually there are additional constraints that affect the scheduling of the activities, such as precedence constraints (for example, an activity cannot start until another one has finished), time constraints (do not start or finish before or later than a certain date) and simultaneously constraints (activities that cannot be done at the same time). In this chapter, different tools for project scheduling will be introduced: graph representation of time and precedence constraints; Gantt chart and load curves; and heuristic and exact algorithms for project scheduling considering different evaluation criteria. Then, a simple case of project scheduling is presented and solved using the described tools, allowing useful comparison between the graph-based approaches and the exact approach of a Mixed Integer Linear Programming (MILP) model implemented in IBM ILOG CPLEX. The implementation and verification procedure followed here allows the enlargement of project applications beyond commercial applications or open literature.

Similar Papers
  • Conference Article
  • Citations4

Continuous Time MILP Models for Multi-Mode Resource Constrained Project Scheduling Problems

  • Feb 01, 2020
  • Guler Ozturk +1
  • Research Article
  • Citations10

Mixed-integer linear programming for project scheduling under various resource constraints

  • Jun 27, 2024
  • European Journal of Operational Research
  • Nicklas Klein +2
  • PDF
  • Research Article
  • Citations8

Review of conventional metaheuristic techniques for resource-constrained project scheduling problem

  • Jan 01, 2022
  • Journal of Project Management
  • Amir Golab +3
  • Research Article
  • Citations37

Artificial Bee colony for resource constrained project scheduling problem

  • Jan 01, 2011
  • International Journal of Industrial Engineering Computations
  • Reza Akbari +2
  • Conference Article
  • Citations3

Skill-oriented priority scheduling for solving the Resource Constrained Project Scheduling Problem

  • Sep 01, 2015
  • Aurelia Ciupe +3
  • Book Chapter

Chemical Reaction Optimization for Solving Resource Constrained Project Scheduling Problem

  • Jan 01, 2020
  • Lecture notes of the Institute for Computer Sciences, Social Informatics and Telecommunications Engineering
  • Ohiduzzaman Shuvo +1
  • Research Article
  • Citations44

MILP and MINLP models for the optimal scheduling of multi-energy systems accounting for delivery temperature of units, topology and non-isothermal mixing

  • Oct 08, 2020
  • Applied Thermal Engineering
  • Luca Moretti +2
  • Conference Article
  • Citations9

Optimization models for reliable long-reach PON deployment

  • Jun 01, 2011
  • Burak Kantarci +1
  • PDF
  • Research Article
  • Citations1

Evaluating the impact of strategic personnel policies using a MILP model: The public university case

  • Dec 20, 2016
  • Journal of Industrial Engineering and Management
  • Rocio De La Torre +2
  • PDF
  • Research Article
  • Citations8

Effective Project Scheduling Under Workspace Congestion and Workflow Disturbance Factors

  • Jan 09, 2014
  • Australasian Journal of Construction Economics and Building - Conference Series
  • Vitaly Semenov +4
  • Book Chapter

Kinematic Model of Project Scheduling with Resource Constrained under Uncertainties

  • Jan 01, 2015
  • Garbi Giuliani Paulineli +3
  • Research Article
  • Citations26

Resource-Constrained Project Scheduling Problem under Multiple Time Constraints

  • Dec 07, 2020
  • Journal of Construction Engineering and Management
  • Feng Kong +1
  • Research Article
  • Citations85

A GRASP × ILS for the vehicle routing problem with time windows, synchronization and precedence constraints

  • Sep 06, 2016
  • Expert Systems with Applications
  • Syrine Roufaida Ait Haddadene +2
  • Research Article
  • Citations1

A Modified Variable Neighbourhood Search Heuristic for the Multi‐Mode Resource Constrained Project Scheduling Problem with A Case Study

  • Jul 01, 2019
  • INCOSE International Symposium
  • Ripon K Chakrabortt +2
  • Research Article
  • Citations29

A hybrid scatter search approach for resource-constrained project scheduling problem in PERT-type networks

  • Jun 29, 2010
  • Advances in Engineering Software
  • Siamak Baradaran +3
Cactus Communications logo

Copyright 2026 Cactus Communications. All rights reserved.