Production lot sizing and scheduling with non-triangular sequence-dependent setup times

Show More
  • Abstract
  • Literature Map
  • References
  • Citations
  • Similar Papers
Abstract

This paper considers a production lot sizing and scheduling problem with sequence-dependent setup times that are not triangular. Consider, for example, a product that contaminates some other product unless either a decontamination occurs as part of a substantial setup time or there is a third product that can absorb ’s contamination. When setup times are triangular then and there is always an optimal lot sequence with at most one lot per product per period (AM1L). However, product ’s ability to absorb ’s contamination presents a shortcut opportunity and could result in shorter non-triangular setup times such that . This implies that it can sometimes be optimal for a shortcut product such as to be produced in more than one lot within the same period, breaking the AM1L assumption in much research. This paper formulates and explains a new optimal model that not only permits multiple setups and lots per product in a period (ML), but also prohibits subtours using a polynomial number of constraints rather than an exponential number. Computational tests demonstrate the effectiveness of the ML model, even in the presence of just one decontaminating shortcut product, and its fast speed of solution compared to the equivalent AM1L model.

Similar Papers
  • Research Article
  • Citations1

Effect of Setup Times and Workload Trigger Levels on Order Review and Release Policies Performance in a Stochastic Dynamic Job Shop with Sequence-Dependent Setup Time — A Simulation Approach

  • Jul 21, 2023
  • Journal of Advanced Manufacturing Systems
  • Sushma Rani +2
  • PDF
  • Research Article
  • Citations9

Improved firefly algorithm with courtship learning for unrelated parallel machine scheduling problem with sequence-dependent setup times

  • Mar 12, 2022
  • Journal of Cloud Computing
  • Xingwang Huang +5
  • Conference Article
  • Citations1

A heuristic algorithm for assembly line balancing with stochastic sequence-dependent setup times

  • May 01, 2017
  • Zeynel Abidin Cil +4
  • Conference Article

An MIP-based heuristic approach to determine production lot size for capacitated single-stage production processes with stochastic demand on parallel machines

  • Mar 01, 2017
  • Supatchaya Chotayakul +1
  • Research Article
  • Citations72

Metaheuristic algorithms for balancing robotic assembly lines with sequence-dependent robot setup times

  • Aug 29, 2018
  • Applied Mathematical Modelling
  • Mukund Nilakantan Janardhanan +4
  • Research Article
  • Citations3

Production Lot Sizes on a Single Imperfect Machine: FPTAS vs ILP models

  • May 01, 2012
  • IFAC Proceedings Volumes
  • K Schemeleva +4
  • Book Chapter
  • Citations3

Scheduling Operations and SMED: Complementary Ways to Improve Productivity

  • Jan 01, 2019
  • Fernando Charrua-Santos +4
  • Research Article
  • Citations5

Single-Machine Order Acceptance and Scheduling Problem Considering Setup Time and Release Date Relations

  • Jul 16, 2020
  • Arabian Journal for Science and Engineering
  • Papatya S Bıçakcı +2
  • Conference Article
  • Citations1

Scheduling policies in multi-product manufacturing systems with sequence-dependent setup times

  • Dec 01, 2011
  • Wei Feng +2
  • Research Article
  • Citations1352

A survey of scheduling problems with setup times or costs

  • Jun 01, 2008
  • European Journal of Operational Research
  • Ali Allahverdi +3
  • Research Article
  • Citations110

Scheduling hybrid flow shop with sequence-dependent setup times and machines with random breakdowns

  • Jun 12, 2008
  • The International Journal of Advanced Manufacturing Technology
  • M Gholami +2
  • Research Article
  • Citations76

An immune algorithm for scheduling a hybrid flow shop with sequence-dependent setup times and machines with random breakdowns

  • Oct 28, 2009
  • International Journal of Production Research
  • M Zandieh +1
  • Research Article

Scheduling problem solving using genetic and greedy algorithms

  • Jan 01, 2017
  • International Journal of Computer Aided Engineering and Technology
  • R Rajkumar +1
  • Conference Article
  • Citations17

Modeling&Solving Flexible Job Shop Problem With Sequence Dependent Setup Times

  • Oct 01, 2006
  • N Imanipour
  • Research Article
  • Citations89

A genetic algorithm for scheduling open shops with sequence-dependent setup times

  • Sep 03, 2019
  • Computers & Operations Research
  • Levi R Abreu +3
Cactus Communications logo

Copyright 2026 Cactus Communications. All rights reserved.