Resource–constrained project scheduling: a heuristic for the multi–mode case

Show More
  • Abstract
  • Literature Map
  • References
  • Citations
  • Similar Papers
Abstract

This paper presents a heuristic solution procedure for a very general resource---constrained project scheduling problem. Here, multiple execution modes are available for the individual activities of the project. In addition, minimum as well as maximum time lags between different activities may be given. The objective is to determine a mode and a start time for each activity such that the temporal and resource constraints are met and the project duration is minimized. Project scheduling problems of this type occur e.g. in process industries. The heuristic is a multi---pass priority---rule method with backplanning which is based on an integration approach and embedded in random sampling. Its performance is evaluated within an experimental performance analysis for problem instances of real---life size with 100 activities and up to 5 modes per activity.

Similar Papers
  • Research Article
  • Citations110

Resource levelling for projects with schedule-dependent time windows

  • Sep 01, 1999
  • European Journal of Operational Research
  • K Neumann +1
  • Research Article
  • Citations182

An efficient hybrid genetic algorithm for scheduling projects with resource constraints and multiple execution modes

  • Nov 20, 2008
  • International Journal of Production Economics
  • Antonio Lova +3
  • Research Article
  • Citations35

Multi-mode resource leveling in projects with mode-dependent generalized precedence relations

  • Dec 16, 2017
  • Expert Systems with Applications
  • Hongbo Li +1
  • Research Article
  • Citations31

An iterated-local-search heuristic for the resource-constrained weighted earliness-tardiness project scheduling problem

  • Oct 02, 2008
  • International Journal of Production Research
  • Francisco Ballestín +1
  • PDF
  • Research Article
  • Citations11

Comparison of Heuristic Priority Rules in the Solution of the Resource-Constrained Project Scheduling Problem

  • Sep 05, 2021
  • Sustainability
  • Osman Hürol Türkakın +2
  • Research Article
  • Citations36

A constraint-based perspective in resource constrained project scheduling

  • Mar 01, 1994
  • International Journal of Production Research
  • G Ulusoy +1
  • PDF
  • Research Article
  • Citations2

Scheduling for Indonesia’s Aircraft Wing Structure Design Project with Critical Path Method and Resource-Constrained Project Scheduling

  • Jan 01, 2018
  • MATEC Web of Conferences
  • Melissa Putri Hidayat +2
  • Research Article

Automatic Clustering and Multi-Directional Scheduling Scheme for Multi-Mode Scheduling Projects

  • Sep 30, 2019
  • Industrial Engineering & Management Systems
  • Hamid Reza Yoosefzadeh
  • Research Article
  • Citations10

Mixed-integer linear programming for project scheduling under various resource constraints

  • Jun 27, 2024
  • European Journal of Operational Research
  • Nicklas Klein +2
  • Book Chapter
  • Citations7

An Organizational Cooperative Coevolutionary Algorithm for Multimode Resource-Constrained Project Scheduling Problems

  • Jan 01, 2014
  • Lixia Wang +2
  • Research Article
  • Citations7

Solving efficiently Decentralized MDPs with temporal and resource constraints

  • Jul 14, 2010
  • Autonomous Agents and Multi-Agent Systems
  • Aurélie Beynier +1
  • Research Article
  • Citations4

An S-graph Based Approach for Multi-Mode Resource-Constrained Project Scheduling with Time-Varying Resource Capacities

  • Aug 01, 2018
  • Chemical engineering transactions
  • Olivér Ősz +1
  • Research Article

A production scheduling and control system for CAR T cell manufacturing

  • Jan 01, 2024
  • Procedia CIRP
  • Tamás Kis +4
  • Research Article
  • Citations456

Resource-Constrained Project Scheduling with Time-Resource Tradeoffs: The Nonpreemptive Case

  • Oct 01, 1982
  • Management Science
  • F Brian Talbot
  • Research Article
  • Citations50

Heuristics for the minimum project-duration problem with minimal and maximal time lags under fixed resource constraints

  • Apr 01, 1995
  • Journal of Intelligent Manufacturing
  • K Neumann +1
Cactus Communications logo

Copyright 2026 Cactus Communications. All rights reserved.