Comparing optimization modeling approaches for the multi-mode resource-constrained multi-project scheduling problem

Show More
  • Abstract
  • Literature Map
  • References
  • Citations
  • Similar Papers
Abstract

PurposeConstruction firms keep minimal resources to maintain productive working capital. Hence, resources are constrained and have to be shared among multiple projects in an organization. Optimal allocation of resources is a key challenge in such situations. Several approaches and heuristics have been proposed for this task. The purpose of this paper is to compare two approaches for multi-mode resource-constrained project scheduling in a multi-project environment. These are the single-project approach (portfolio optimization) and the multi-project approach (each project is optimized individually, and then heuristic rules are used to satisfy the portfolio constraint).Design/methodology/approachA direct search algorithm called Probabilistic Global Search Lausanne is used for schedule optimization. Multiple solutions are generated that achieve different trade-offs among the three criteria, namely, time, cost and quality. Good compromise solutions among these are identified using a multi-criteria decision making method, Relaxed Restricted Pareto Version 4. The solutions obtained using the single-project and multi-project approaches are compared in order to evaluate their advantages and disadvantages. Data from two sources are used for the evaluation: modified multi-mode resource-constrained project scheduling problem data sets from the project scheduling problem library (PSPLIB) and three real case study projects in India.FindingsComputational results prove the superiority of the single-project approach over heuristic priority rules (multi-project approach). The single-project approach identifies better solutions compared to the multi-project approach. However, the multi-project approach involves fewer optimization variables and is faster in execution.Research limitations/implicationsIt is feasible to adopt the single-project approach in practice; realistic resource constraints can be incorporated in a multi-objective optimization formulation; and good compromise solutions that achieve acceptable trade-offs among the conflicting objectives can be identified.Originality/valueAn integer programming model was developed in this research to optimize the multiple objectives in a multi-project environment considering explicit resource constraints and maximum daily costs constraints. This model was used to compare the performance of the two multi-project environment approaches. Unlike existing work in this area, the model used to predict the quality of activity execution modes is based on data collected from real construction projects.

Similar Papers
  • PDF
  • Research Article
  • Citations11

Comparison of Heuristic Priority Rules in the Solution of the Resource-Constrained Project Scheduling Problem

  • Sep 05, 2021
  • Sustainability
  • Osman Hürol Türkakın +2
  • Research Article
  • Citations71

Multi-mode resource constrained project scheduling: scheduling schemes, priority rules and mode selection rules.

  • Dec 12, 2006
  • INTELIGENCIA ARTIFICIAL
  • A Lova +2
  • Conference Article
  • Citations8

BPGA-EDA for the multi-mode resource constrained project scheduling problem

  • Jul 01, 2016
  • Mayowa Ayodele +2
  • Book Chapter

Computational Studies

  • Jan 01, 2001
  • Alf Kimms
  • Research Article
  • Citations28

Multi-agent technology for scheduling and control projects in multi-project environments. An Auction based approach

  • Jun 30, 2009
  • INTELIGENCIA ARTIFICIAL
  • José Alberto Arauzo +3
  • Research Article
  • Citations187

A Hybrid Genetic Algorithm for Assembly Line Balancing

  • Nov 01, 2002
  • Journal of Heuristics
  • José Fernando Gonçalves +1
  • PDF
  • Research Article
  • Citations8

Effective Project Scheduling Under Workspace Congestion and Workflow Disturbance Factors

  • Jan 09, 2014
  • Australasian Journal of Construction Economics and Building - Conference Series
  • Vitaly Semenov +4
  • Research Article
  • Citations37

An improved robust buffer allocation method for the project scheduling problem

  • Aug 02, 2016
  • Engineering Optimization
  • Parviz Ghoddousi +2
  • PDF
  • Research Article

Using Computer Simulations to Plan Construction Projects Accurately

  • Sep 21, 2019
  • Alberta Academic Review
  • Alison Smith +2
  • Research Article

Efficient scheduling of multiple software projects for work continuity and identical completion time

  • Feb 21, 2025
  • MethodsX
  • Abdulrahman Aldhubaiban +1
  • Research Article
  • Citations7

Mode generation rules to define activity flexibility for the integrated project staffing problem with discrete time/resource trade-offs

  • May 21, 2020
  • Annals of Operations Research
  • Mick Van Den Eeckhout +2
  • Conference Article

Entropy weight fuzzy synthetic evaluation-based risk evaluation for real estate agent construction project

  • Apr 01, 2011
  • Lian-Fa Ruan +1
  • Research Article
  • Citations56

Multiple Modular Building Construction Project Scheduling Using Genetic Algorithms

  • Oct 31, 2018
  • Journal of Construction Engineering and Management
  • Jeonghoon Lee +1
  • Conference Article
  • Citations1

Probabilistic Model Enhanced Genetic Algorithm for Multi-Mode Resource Constrained Project Scheduling Problem

  • Jul 11, 2015
  • Mayowa Ayodele +2
  • Research Article
  • Citations182

An efficient hybrid genetic algorithm for scheduling projects with resource constraints and multiple execution modes

  • Nov 20, 2008
  • International Journal of Production Economics
  • Antonio Lova +3
Cactus Communications logo

Copyright 2026 Cactus Communications. All rights reserved.