Abstract

The development of road or toll road infrastructure in a country can be used as a benchmark to determine the level of economic progress of a country, both macro and micro. The location of toll exits has a significant effect in absorbing labor and creating new business activities. Projects are dynamic, so contractors must be responsive to changes in situations and conditions on the project, if they want to succeed in reaping optimum profits. Aspects of planning a highly competitive construction at this time are very demanding on accuracy, effectiveness, efficiency, and economy in analyzing a project. In the world of construction projects, there are many things that can be done, one of which is cost control. In controlling costs, efforts can be made so that the realization of costs that occur is in accordance with the needs of implementation and is not excessive, such as cost suppression efforts, namely making savings without reducing quantity or quality. The Earned Value Method is used to determine project performance in terms of costs at one time, determine project performance in terms of schedule/time at one time, estimate costs to complete the project after the evaluation time and estimate the time to complete the project after the evaluation. In this research the author carried out a cost analysis using the Earned Value Method on the preservation of the Section 5 Pandaan Malang Toll Exit Road.

Loading PDF

Similar Papers
  • Research Article

The Risks of Toll Road Infrastructures in Indonesia

  • Jan 14, 2012
  • SSRN Electronic Journal
  • Lukas B Sihombing +3
  • Research Article
  • Citations22

Team performance and information system implementation

  • Apr 19, 2008
  • Information Systems Frontiers
  • Malgorzata Plaza
  • Research Article

Project Cost Performance Analysis Using the Earned Value Method on the Laga Collector's Highway Improvement Project – Bauguia, Timor-Leste

  • Aug 18, 2024
  • THE SPIRIT OF SOCIETY JOURNAL
  • Laurenco Luis +2
  • Conference Article
  • Citations4

Research on Target Cost Management of Construction Project with VBQ Based on EVM

  • Jan 01, 2009
  • Bing Xu
  • Research Article
  • Citations1

The impact of toll road exit infrastructure development on land use and land values in adjacent areas (Case: eastern toll road exit in Probolinggo Regency)

  • Jun 06, 2022
  • Journal of Sustainability Science and Technology
  • Okky Fransila Arganata +1
  • PDF
  • Research Article
  • Citations3

ANALYSIS OF COST CONTROL, TIME, AND QUALITY ON CONSTRUCTION PROJECT

  • Mar 01, 2018
  • Journal of Management and Business
  • Dewi Nusraningrum +1
  • Research Article
  • Citations12

Using Earned Value Methods to Substantiate Change-of-Scope Claims

  • Mar 01, 2002
  • Engineering Management Journal
  • Paul Kauffmann +2
  • PDF
  • Research Article
  • Citations28

Earned Value Method (EVM) for Construction Projects: Current Application and Future Projections

  • Mar 04, 2022
  • Buildings
  • Mayra Proaño-Narváez +3
  • Research Article

Cost Performance Evaluation of The Improvement of The Wirosari-Karangasem Road Section, Wirosari District Uses Method (Earned Value Concept)

  • Jan 27, 2025
  • International Journal of Sustainable Building, Infrastructure and Environment (IJOSBIE)
  • Arie Kris Irawan +2
  • PDF
  • Research Article

A Guideline of Earned Value Method (EVM) Implementation as Decision Baseline on Acceleration Solutions for Construction Project Scheduling

  • Oct 29, 2023
  • Technium: Romanian Journal of Applied Sciences and Technology
  • Zetta Rasullia Kamandang +2
  • Conference Article
  • Citations22

A Management System for Cut and Fill Earthworks Based on 4D CAD and EVMS

  • Jun 24, 2005
  • Nobuyoshi Yabuki +1
  • PDF
  • Research Article
  • Citations3

Development and Application of Models for Landslide Hazards in Northern Pakistan

  • Aug 17, 2022
  • Sustainability
  • Tahir Ali Akbar +8
  • Book Chapter

Modernisation of Transport Infrastructure and Changes in Spatial Accessibility

  • Jan 01, 2022
  • Jędrzej Gadziński +1
  • Research Article
  • Citations1

Optimalisasi Biaya dan Waktu Proyek Kontruksi Pelebaran Jalan Menggunakan Earned Value

  • Oct 31, 2021
  • Jurnal Manajemen Teknologi & Teknik Sipil
  • Sentot Tri Wibowo +4
  • PDF
  • Research Article

A Multi-stage Scheme Decision Model for Complex Products Based on Prospect Theory and Earned Value Method

  • Jan 01, 2023
  • SHS Web of Conferences
  • You Peng +2
Cactus Communications logo

Copyright 2026 Cactus Communications. All rights reserved.